Q436. A constructive approach in which no commitment is made unless it is necessary to do so, is ____________

  • a) Least commitment approach
  • b) Most commitment approach
  • c) Nonlinear planning
  • d) Opportunistic planning

✅ Correct Answer: A) Least commitment approach

Explanation: Because we are not sure about the outcome.